PM · Schedule Editor

Plan the schedule, the budget, the team

Edit the Phase → Milestone → Task tree for any project. Rename, shift dates, retarget budgets and change status. Every change propagates to designers' timesheets and is captured in the revision log.

Back to Timesheet
Read-only preview
Only the Project Manager role can save schedule changes. Switch role from your profile to try editing.
Project
Schedule · SG-1042

Capella Sentosa — Tower B

Project fee
$1,465,000
incl. $45,000 VO
Total budget
3,340 h
Est. labor cost
$531,060
Est. margin
63.8%
Phases
3
Phase 1 · Concept DesignDone01 Mar – 30 Apr · 410/420hBudget $66,780
M1.1 · Concept sign-offDoneDue 30 Apr· 56h budgeted· $8,904
  • Lobby material board v3
    10 – 18 Apr · due 18 Apr
    Done
  • Concept narrative deck
    01 – 25 Apr · due 25 Apr
    Done
Phase 2 · Schematic DesignOn track01 May – 30 Jun · 940/1280hBudget $203,520
M2.1 · Guest room packageOn trackDue 30 Jun· 108h budgeted· $17,172
  • Guest Room Layout — Typical Floor
    01 – 20 Jun · due 20 Jun
    On track
  • Bathroom set-out & FF&E loose
    10 – 30 Jun · due 30 Jun
    At risk
M2.2 · Public areas packageAt riskDue 30 Jun· 36h budgeted· $5,724
  • Corridor & lift lobby package
    12 – 28 Jun · due 28 Jun
    At risk
Phase 3 · Design DevelopmentUpcoming01 Jul – 30 Sep · 0/1640hBudget $260,760
M3.1 · DD set 60%UpcomingDue 15 Aug· 80h budgeted· $12,720
  • Joinery elevations — typical room
    01 Jul – 10 Aug · due 10 Aug
    Upcoming
Contract change control

Variation orders

Approved $45,000Pending $18,000
  • VO-001Ballroom acoustic upgradeApproved
    2026-05-14 · $45,000 · 120h
    Client requested premium acoustic treatment.
  • VO-002Additional CGI rounds — public areasSubmitted
    2026-06-02 · $18,000 · 60h